Carney refers the Whitehorse Power Centres project to the Major Projects Office, with 15 megawatts by 2028 and up to $73 million in federal investment
Politics · Whitehorse · The Canadian Chronicle
Published Friday, November 27, 2026 · 3 min read

The Yukon's power shortage now has a federal fast track.
Prime Minister Mark Carney announced in Whitehorse on Thursday evening that the Whitehorse Power Centres project will be referred to the Major Projects Office, the federal office created to advance projects of national interest. The referral is meant to help advance a project the Prime Minister's Office calls critical to meeting growing electricity demand in the Yukon.
What the project builds
The project proposes to begin with two new thermal power plants, a new electrical substation, and associated transmission infrastructure in Whitehorse. The initial phase would add 15 megawatts of generation capacity by 2028.
Future phases would expand capacity up to approximately 150 megawatts. The project represents a federal investment of up to $73 million through the Build Communities Strong Fund, creating local contracting opportunities and permanent jobs once the plants are operating.
The Major Projects Office will support the Government of Yukon in assessing the grid upgrades needed to accommodate the new generation and transmission, including an evaluation of residential and industrial demand, investment opportunities for Indigenous partners and the private sector, and the appropriate fuel types and locations.
A northern energy package
The Whitehorse referral sits alongside two other northern projects already referred to the office: the Taltson Hydro Expansion and the Iqaluit Nukkiksautiit Hydro Project. Ottawa is also advancing the Mayo Hydro Facility and the Atlin Hydro Expansion with territorial and Indigenous partners, and Budget 2026 proposes $1.6 billion over 10 years, starting in 2027–28, to improve energy reliability in the North.
“Today's referral of the Whitehorse Power Centres project is one of a series of projects, including the proposed Yukon-British Columbia Grid Connect and other hydropower opportunities, that will provide reliable, affordable, and secure energy to power the Yukon's future,” Carney said.
One day, three stops
The announcement closed a three-stop day. Earlier Thursday, Carney was in Yorkton, Saskatchewan, campaigning for the December 7 byelection in Yorkton—Melville alongside Liberal candidate Aaron Kienle; he noted he was the first Liberal prime minister to visit the community since 1910.
In Regina, he met Premier Scott Moe behind closed doors to talk about the economy, electricity and trade. Moe, asked whether he was endorsing any candidate in the byelection, said he is staying out of the race. Carney then met Yukon Premier Currie Dixon in Whitehorse before the power announcement.
Sources
- Prime Minister of Canada, news release, November 26, 2026 — Whitehorse Power Centres project referred to the Major Projects Office
- The Canadian Press, November 26, 2026 — Carney meets Moe in Regina, campaigns in Yorkton, announces in Whitehorse